The process
The process for installing photovoltaic systems is now a quick and easy affair.
Study
Property and photovoltaic system assessment
Submission of the connection application to the provider
Electronic submission of the connection application to the provider via the TAXIS system, using the applicant’s credentials.
The utility service will be in the applicant’s name.
If the application file is complete, the provider will notify the interested party within fifteen working days.
The utility service will be in the applicant’s name.
If the application file is complete, the provider will notify the interested party within fifteen working days.
Connection cost
The connection cost is determined by DEDDIE. Typically, for single-phase connections, it is 370 + VAT, and for three-phase connections, it is 390 + VAT.
Signing of the Association Agreement
The signing of the Connection Agreement and the simultaneous payment of the relevant cost must take place within 60 days.
Submission of the training application
Submission of the application for the conclusion of an Energy Net Metering Agreement.
Signing of the Agreement
Signing of the Energy Net Metering Agreement with the Supplier.
Installation of the photovoltaic system
Installation of the photovoltaic system, for which there is a 12-month deadline from the signing of the Connection Agreement.
Application for connection activation
Upon completion of the construction of the power generation plant, the application for the activation of the connection is also submitted.
Declaration of readiness and activation of the connection
This is followed by the declaration of readiness and the activation of the connection, with a 12-month deadline from the signing of the Connection Agreement. The duration of the Net Metering Agreement is twenty-five (25) years.